WORK EXPERIENCES RECORD - CONSTRUCTION WORKS

 
  Item Project Contruction Period Commencial Date Completion Date Progress % Gallery  
  1. Hacking & Demolish of 7 unit Show House Including 1 Unit Sales Gallery at Setia Tropika Show Village. (SP Setia Sdn Bhd) 2 Months November 2013 January 2014 100% Image  
  2. Hacking & Demolition of Internal BrickWall at Paradigm Mall (Kemayan City), JB. (WCT Land Sdn Bhd) 3 Months September 2013 December 3013 100% Image  
  3. Demolition & Hoarding Works For Proposed Developmentat Bandar Johor Bahru, Daerah Johor Bahru, Johor. (PanGlobal Plaza) 3 Months March 2013 June 2013 100 % Image  
  4. Hacking & Clearing of Ready Mix Concrete Plant at Medini, Nusajaya. (Buildcon Concrete Sdn Bhd Group of YTL) 2 Months Febuary 2013 April 2013 100% Not Image  
  5. Demolition Work For 7 Units Show Houses For Setia Indah Sdn Bhd @ Taman Setia Tropika, Mukim Tebrau 7 Weeks September 2012 November 2012 100% Not Image  
  6. Demolishing & Hacking Work of Show House 8 weeks May 2012 July 2012 100% Not Image  
  7. Hacking & Demolish 5 Units Bangalow Structure @ Starhill, Kempas 4 Weeks May 2012 June 2012 100% Not Image  
  8. Demolition Works For 10 Units Show Houses At Show Village, Setia Eco Garden @ Gelang Patah 8 Weeks January 2012 March 2013 100% Not Image  
  9. Demolition, Site Clearing & Earthwork For 1 Unit Single Storey Bungalow @ Taman Kebun Teh, J.B 3 Weeks January 2012 January 2012 100% Not Image  
  10. Demolition Of Pedestrian, Covered Platform And RC Footing At KTMB 6 Weeks November 2011 January 2012 100% Not Image  
 